fort st vrain power plant

Fort Saint Vrain Generating Co

Colorado, USA

Completed 2020

fort st vrain power plant
Fort Saint Vrain
Generating Company
Denver, Colorado, USA

Investor

Gas Path Upgrades
Updated Electrical / I&C

Primary Service

$700,000

Value

1 Lead
15 Journeyman
1 Millwright

Architecture

Project Profile

fort st vrain power plant

Hot Gas Path Upgrade with the DLN 2.6+ upgrade package.

Goal

• Installation of the CDM System (Generation Mark VI-e)
• Installation of the Op-flex auto-tune package
• Installation of the electronic fuel valves
• Installation of the Hazardous Gas System (HAZ-GAS); including 5 Haz-Gas Panels
• Work with site personnel to relocate the Aux Panel into the permanent location
• Install Aux panel & PAMC/Controller components into Aux Panel
• Weld conduit supports as required
• Build and install new probe holders
• Install conduit ring, and run sensor cables to JB1000
• Install JB1000 and land all wires

Scope of Work

Minimal On-site Services support from customers due to the COVID-19 Pandemic. Many customer plant staff members originally scheduled to support the outage were not available at the start time of the outage due to COVID-19. SG received notice of this situation on the 1st day we arrived on site.

Challenges

Drawing on our successful experience with a DLN 2.6+ upgrade at a site in Wisconsin, USA, SG assisted in appointing SGF as the Project Lead and System Experts for the comprehensive turbine and control room electrical scope.

Solutions